About This Project

Industry Civil

Budget

$5 Million

Contract

2019 

Location

Thornton

Overview

Goldspring was contracted to deliver a 72 lot subdivision over 3 stages throughout 2019. The staging was completed to that the subsequent stage was commencing while the previous stages were completed. The total project duration was 7 months from clearing to final council signoff.

The construction was undertaken using 'in house' resources with all plant and equipment provided from Goldspring fleet.

Scope

  • Clearing
  • Bulk earthworks
  • Water and Sewer
  • Utilities
  • Pavements
  • Concrete works

Highlights

  • Construction of pavements on reactive clays
  • High level of environmental compliance
  • No MTI or LTI's recorded
  • Construction of large detention basin and stormwater management strategy