About This Project
Industry Civil
Budget
$5 Million
Contract
2019
Location
Thornton
Overview
Goldspring was contracted to deliver a 72 lot subdivision over 3 stages throughout 2019. The staging was completed to that the subsequent stage was commencing while the previous stages were completed. The total project duration was 7 months from clearing to final council signoff.
The construction was undertaken using 'in house' resources with all plant and equipment provided from Goldspring fleet.
Scope
- Clearing
- Bulk earthworks
- Water and Sewer
- Utilities
- Pavements
- Concrete works
Highlights
- Construction of pavements on reactive clays
- High level of environmental compliance
- No MTI or LTI's recorded
- Construction of large detention basin and stormwater management strategy